Alabama Emmaus Community - Agape Room Timeline

Camp Sumatanga

All schedule times and materials are preliminary estimates based upon preliminary plans and specifications to provide the community the opportunity to make donations.

Final schedule and quantities will be determined after issuance of final plans and specifications as well as the response from the community for donated labor and materials.
Item Description &
Scheduled Dates
Activities Materials Equipment Comments

Foundation
Sept. 3 - 7

Site preparation

Footings



Masonry





Reinforcing steel - 1,000 lbs #5, 50 lbs #3 and steel supports;  Concrete - 10 CY of 3,000psi ready-mix concrete

Block - 60 each 12" cmu, 60 each 12" form block, fine sand & type S mortar

Uni-loader,
backhoe

Uni-loader,
backhoe


Mortar mixer,
masonry tools


Building layout will be
provided by GC

Slab on Grade
Sept. 10 - 15

Termite Treatment

Floor slab


10 CY of gravel fill #57;  1 roll of 6mil poly vapor barrier;  4 sheets of wire mesh (4x4 10/10);  9 CY of ready-mix3000psi concrete



Hand tools



Need qualified
concrete finishers


Load-bearing Masonry
Sept. 17 - 22

Masonry

Block - 825 each 12" cmu, 100 each 12" 'U' block, fine sand & type S mortar;  Concrete - 8 CY of 3,000psi block fill;  Weld plates

 


Mortar mixer,
masonry tools
 

Floor System
Sept. 24 - Oct. 3

Structural Steel

 

Elevated Slab


Bar joist (14K4), bridging, metal deck (16ga)

Concrete - 6 CY


Forklift, welding machine

Concrete pump


Need qualified
steel erectors

Need qualified
concrete finishers


Framing
Oct. 4 - 13

Wall Framing






Roof Framing

2x Framing - 7 each 2x4x14' treated, 70 each 2x4x14', 6 each 2x8x14';  Sheathing - 26 sheets 5/8" OSB, 1 roll Tyvek house wrap;  Miscellaneous nails and hardware

Laminated wood decking; 4 rolls of 30# felt; 1 roll of ice & water shield; miscellaneous 2x, nails and hardware

Hand tools






Hand tools
 

Finishes
Oct. 15 - Nov. 3

Exterior Finishes





Interior Finishes

Siding to match existing, relocate existing windows, shingles to match existing (8sq), gutters & downspouts, painting and other miscellaneous items

Paneling to match existing, 5/8" gypsum board (35 sheets), batt insulation, wood base, drywall finish, wood doors & frames, floor covering, painting, and other miscellaneous items

Hand tools




Hand tools

 
 

Other Items
Throughout Project

 

Demolition


Fire Protection
Mechanical
Electrical

 

Saw cut new openings and remove existing items

 

 

Need qualified
contractors

Return to Main Page