schedule times and materials are preliminary estimates based upon
preliminary plans and specifications to
provide the community the opportunity to make donations. Final schedule and quantities will be determined after issuance of final plans and specifications as well as the response from the community for donated labor and materials. |
||||
| Item
Description & Scheduled Dates |
Activities | Materials | Equipment | Comments |
Foundation Sept. 3 - 7 |
Site preparation Footings Masonry |
Reinforcing steel - 1,000 lbs #5, 50 lbs #3 and steel supports; Concrete - 10 CY of 3,000psi ready-mix concrete Block - 60 each 12" cmu, 60 each 12" form block, fine sand & type S mortar |
Uni-loader, backhoe Uni-loader, backhoe Mortar mixer, |
Building layout will be provided by GC |
Slab on Grade Sept. 10 - 15 |
Termite Treatment Floor slab |
10 CY of gravel fill #57; 1
roll of 6mil poly vapor barrier; 4
sheets of wire mesh (4x4 10/10); 9
CY of ready-mix3000psi concrete |
Hand tools |
Need qualified |
Load-bearing Masonry Sept. 17 - 22 |
Masonry |
Block - 825 each 12" cmu, 100 each 12" 'U' block, fine sand & type S mortar; Concrete - 8 CY of 3,000psi block fill; Weld plates
|
Mortar mixer, masonry tools |
|
Floor System Sept. 24 - Oct. 3 |
Structural Steel
Elevated Slab |
Bar joist (14K4), bridging, metal deck (16ga) Concrete - 6 CY |
Forklift, welding machine Concrete pump |
Need qualified steel erectors Need qualified |
Framing Oct. 4 - 13 |
Wall Framing Roof Framing |
2x Framing - 7 each 2x4x14' treated, 70 each 2x4x14', 6 each 2x8x14'; Sheathing - 26 sheets 5/8" OSB, 1 roll Tyvek house wrap; Miscellaneous nails and hardware Laminated wood decking; 4 rolls of 30# felt; 1 roll of ice & water shield; miscellaneous 2x, nails and hardware |
Hand tools Hand tools |
|
Finishes Oct. 15 - Nov. 3 |
Exterior Finishes Interior Finishes |
Siding to match existing, relocate existing windows, shingles to match existing (8sq), gutters & downspouts, painting and other miscellaneous items Paneling to match existing, 5/8" gypsum board (35 sheets), batt insulation, wood base, drywall finish, wood doors & frames, floor covering, painting, and other miscellaneous items |
Hand tools Hand tools |
|
|
Other Items |
Demolition |
Saw cut new openings and remove existing items |
Need qualified |
|